PENERAPAN METODE LINE OF BALANCE (LOB) DALAM OPTIMALISASI JADWAL PEMBANGUNAN PERUMAHAN GRAHA ALAM SUTRA

Authors

  • Anwar Matoha Universitas Bina Taruna Gorontalo
  • Mohamad Januar Fuad Universitas Bina Taruna Gorontalo
  • Ari Putra Rachman Universitas Bina Taruna Gorontalo

DOI:

https://doi.org/10.37971/radial.v13i1.512

Keywords:

Line of Balance, Project Scheduling, S-Curve

Abstract

This study aims to apply and analyze the Line of Balance (LoB) method for scheduling the construction of 20 type 36/108 houses in the Graha Alam Sutra Housing Complex, Hutuo Village, Limboto District, Gorontalo Regency. The research questions include the technical application of the LoB method and the evaluation of project scheduling results after implementing the method. Research data includes the S-curve, Cost Estimate Plan (CEP), network planning, and field data. The LoB method is applied through the development of a Work Breakdown Structure (WBS), activity logic diagram, and LoB graph for one house unit, which is then scaled up to 20 units simultaneously and linearly. Adjustments were made to the RAB, S-curve, and work sequence to prevent conflicts (crosses) between activities. The research results show that the LoB method successfully identified the project's critical path, minimized time deviations, and improved work rotation efficiency and field supervision. The project was completed in 110 calendar days with balanced work distribution across weeks. In conclusion, the LoB method proved effective for large-scale housing construction projects, producing a more structured, efficient, and easily monitored schedule compared to conventional methods.

References

Aulia, Muhammad Abrar, Aulia Hashemi Farisi, M. Agung Wibowo, and Arif Hidayat. 2017. “Balance Pada Proyek Konstruksi Repetitif ( Studi Kasus : Proyek Pembangunan Apartemen.” Jurnal Karya Teknik Sipil 6(1): 211–19.

Fuad, Mohamad Januar, and Ari Putra Rachman. 2024. “PENJADWALAN DAN ALOKASI MATERIAL PADA PROYEK PENINGKATAN RUAS JALAN KANTO-PULAHENTI DENGAN MENGGUNAKAN METODE LOB ( LINE OF BALANCE ) Judul Skripsi “ Penjadwalan Dan Alokasi Material Pada Proyek Peningkatan Ruas Jalan.” 12(2): 340–50.

Fuad, Mohammad Januar. 2019. “Penjadwalan Dan Alokasi Material Dengan Metode Line of Balance.” Jurnal Peradaban Sains, Rekayasa, dan Teknologi 7(2): 153–61.

Kalia, Sri Mutianingsi, Arfan Utiarahman, and Mohamad Yusuf Tuloli. 2022. “Penerapan Metode Line of Balance Pada Proyek Konstruksi Repetitif (Studi Kasus : Perumahan Griya Tunas Mandiri).” Jurnal Penelitian Jalan dan Jembatan 2(2): 35–46. doi:10.59900/ptrkjj.v2i2.85.

Laia, F. 2020. “Penerapan Metode Line Of Balance Pada Penjadwalan Proyek Jalan Preservasi Teluk Dalam-Lolowau.” Pengetahuan dan Sikap Dalam Penelitian Kesehatan: 1–147.

Lestari, D. 2018. “Penerapan Metode Line of Balance Pada Pembangunan Perumahan (Studi Kasus Pada Perumahan Permata Puri Ngaliyan Semarang).” Jurnal Teknik Sipil. http://203.89.29.50/index.php/jts/article/view/802.

Putra, I Komang Alit Astrawan, I Wayan Diasa, Ni Ketut Sri Astati Sukawati, I Gusti Ngurah Eka Pratama, and I Made Yogi Antara Putra. 2023. “Perbandingan Metode Penjadwalan Line Of Balance (LoB) Dengan Precedence Diagram Method (PDM) Pada Proyek Kontruksi Repetitif.” Vastuwidya 6(1): 9–24.

Soplanit Nony, Maelissa Nelda, and Henriette D. Titaley. 2021. “Analisis Penerapan Metode Line of Balance Pada Pembangunan Rumah Susun Pemkab Kepulauan Tanimbar.” Jurnal Simetrik 11(2): 474–79.

Studi, Program, D-iv Teknik Perancangan, Jalan Dan, Jembatan Konsentrasi, Jurusan Teknik Sipil, and Politeknik Negeri Jakarta. 2023. “LINE OF BALANCE PADA PROYEK KONSTRUKSI.” (03).

Sudarson, Willim. 2020. “Evaluasi Penjadwalan Proyek Dengan Metode Line of Balance (Studi Kasus : Hotel Santika Batam).” Journal of Civil Engineering and Planning 1(2): 85. doi:10.37253/jcep.v1i2.715.

Downloads

Published

2025-06-30